Blog

November 5, 2025
5 min

Asterra October performance overview

article

In October, we continued steady development activity at Asteres Village, with construction progressing on multiple residential buildings and supporting infrastructure. Work progressed on six houses and a guest house, and preparation work continued in the Phase Two territory. In addition, production of one CLT building was completed at the factory.

The month also saw ongoing interest from potential buyers through on-site visits. Looking ahead, the demo house will be opened in mid-November, marking an important step in the sales process and offering potential buyers the opportunity to explore the village concept and building quality firsthand.

On the Asterra platform, funding activity remained stable and aligned with village development needs, supporting the project's long-term progress.

Platform key indicators

  • Total funding available on the platform - 500,000
  • Lenders joined - 88 (total active lenders - 680)
  • New funding attracted - 702,141 (total funding - €4,300,950)
  • Lenders' interest earned in the given month - 79,904 (total - 373,157)
  • Average interest rate - 16.12%

Village project statuses

Brief status report on construction works in Asteres Village during October.

  • Construction work has commenced on six houses, one guest house, and on phase two territory.
    • Draugu 6 - various indoor works - sanding and painting of CLT panels, tiling and waterproofing works, completed designer floor installation. Fence construction is still in progress.
    • Draugu 8 - underfloor heating was installed, dry concrete (Estrich) was laid, and house insulation works were done. Installation of vertical and horizontal battens was completed.
    • Draugu 11 - completed electrical installation and facade installation; also completed building drywall partitions. Landscaping and gardening works were done.
    • Draugu 13 - CLT assembly work is complete, and roof trusses have been installed, along with vapour barrier insulation.
    • Draugu 17 - completed installation of CLT and roof frame assembly
    • Draugu 21 - foundation works completed. Built a driveway.
    • Asteru 2 - The building permit is in the approval process. Construction works have not yet started.
    • Guest house - the old building has been demolished, and foundation work of the new building has started.
    • Phase 2 - approximately 20,000 m³ of sand have been excavated from the small lake/quarry within the village

  • Manufacturing of one CLT building (Draugu 21) has been completed in the factory.
  • Active sales operations continue, resulting in potential buyers visiting the Village.

  • Construction Materials Used:
    • 52,9 tons of crushed stone delivered.
    • 9 cubic meters of ready-mix concrete were used for building foundations.
    • 18 cubic meters of sand were delivered.

You may like these articles:

article
April 10, 2026
4 min

March performance overview

March has been a whirlwind of activity at Asterra Estate. While we’ve been busy keeping the hammers swinging and the concrete pouring at Asteres Village, the real highlight happened on the platform itself. In March, we officially surpassed 1,000 active lenders! We love seeing our community grow. It’s a sign that our lenders believe in our vision, and we’re happy to have every single one of you on board. Here is a brief overview of how March went for us.

article
April 3, 2026
1 min

Easter Holiday schedule

As we celebrate this joyful holiday, we’d like to let you know that our team will be taking a short Easter break. From April 3 to April 6, response times may be a bit slower than usual. We’ll be back to full availability on April 7, ready to assist you as always. Thank you for your understanding, and we wish you a warm and happy Easter! 🌷

article
April 1, 2026
5 min

Strategic bank partnership to accelerate Asteres Village development

Asterra Estate has reached a strategic agreement with one of Latvia’s lead banks to support the refinancing of homes within the Asteres Village project. It’s a really positive sign for the work we’re doing at Asteres Village and a meaningful boost for the project’s future.