Performance report. July

article

July marked the second month of Asterra Estate’s active operations, and the project continued to gain impressive traction in both investor engagement and construction progress. Lenders remained highly involved, contributing a total of €1.388 million in funding for Asterra Village projects during the month alone — a strong indicator of growing confidence in the development’s vision and potential.

On the ground, construction activities moved ahead at full speed. A total of six buildings have now entered the construction phase, with individual houses progressing through various stages of development. At the same time, groundwork began on the first of the planned Guest Houses — a thoughtfully designed complex that will feature multiple buildings, padel tennis courts, and a variety of leisure amenities aimed at enhancing the lifestyle within the Asterra Village community.

Platform key indicators

  • Total funding available on the platform - 1,380,000
  • Lenders joined - 188 (total active lenders - 450)
  • New funding attracted - 1,388,759 (total funding - €2,719,541)
  • Lenders' interest earned in the given month - 103,617 (total - 183,855)
  • Average interest rate - 16.42%

Village project statuses

Brief status report on construction works in Asteres Village during July.

  • Building permit for the Guest house project has been received. Additionally, for Draugu iela 1 and Draugu iela 14, work is in progress for obtaining a building permit.
  • Construction work has commenced on five houses
    • Draugu 8 and 13 – foundation construction completed
    • Draugu 17 and 21 – land preparation and foundation construction are underway, construction of external utility networks completed
    • Draugu 11 - installation of CLT and roof trusses
    • Draugu 6 - installation of Estrich floors, underfloor heating system, and ThermoWhite floor insulation has been completed. Ceiling structure installation is ongoing. Final touches on facade works are in progress. Paving works have started.
  • Manufacturing of one CLT building (Draugu 13) has started in the factory
  • Active sales operations began in June, resulting in the first potential buyer visits to the Asteres village. Potential buyers’ visits to the Village also continued in July.
  • Construction Materials Used:
    • 346,5 tons of crushed stone delivered
    • 59 cubic meters of concrete were used for building foundations
    • 930 square meters of reinforcement mesh used
    • 2,1 tons of reinforcement steel used

You may like these articles:

article
December 4, 2025
4 min

Asterra November performance overview

November has been another busy month at Asteres Village. Construction kept going strong - we kicked off work on eight homes in total - seven residential homes and one guest house. Some houses are already getting their windows and facades done, others have foundations and roofs in place, and inside these homes, the team is busy with sanding, painting, and installing underfloor heating. All in all, things are really starting to take shape!

article
November 24, 2025
3 min

This holiday, your bonus might come with a boarding pass to Asterra Estate.

The holiday season is almost here, and at Asterra Estate, we’re celebrating with something special. This year, your investments might send you on a weekend getaway to one of Latvia’s most charming new real estate developments.

article
November 14, 2025
1 min

Support availability during National Holidays

🇱🇻 Latvia’s Independence Day is almost here, and our Asterra Estate team will be off celebrating from November 15th to 18th.