Blog

January 7, 2026
4 min

Asterra December performance overview

article

December was a productive month for Asterra Estate. Alongside consistent platform activity, the community continued to grow— over the past seven months, Asterra Estate has reached more than 700 loyal lenders, with more than €5 million committed to the project. During the month, we also activated the Early Exit option for the first projects, giving investors greater flexibility, and shared plans to expand beyond residential development with a CLT & GLT production factory to support more efficient construction and long-term growth.

At the same time, progress across the village remained steady, with multiple houses advancing through interior, exterior, and infrastructure works. Below you’ll find a detailed overview of the platform’s key indicators and the latest project statuses from the village.

Platform key indicators

  • €626,708 mezzanine loans attracted
  • €87,770 interest earned
  • 16.03% average interest rate
  • €6,679 average funding amount
  • 87 new active lenders joined Asterra

Village project statuses

  • Draugu iela 6 - interior works (wall painting, plastering and tiling, also installation of parquet and interior doors) and furniture placement and assembly
  • Draugu iela 8 - completed work on the terrace construction. Installed polished concrete (Ultratop) floors. Started construction of an outdoor utility room and front deck, and also began interior works (tiling and plastering).
  • Draugu iela 11 - wall and ceiling painting, plastering and tiling works have been completed. Started construction of an outdoor utility room. Completed installation of exterior doors
  • Draugu iela 13 - completed installation of drywall installation on the ceilings. Installation of the facade board and CLT sanding has started
  • Draugu iela 14: construction of the sewage network and assembly of the foundation formwork have been completed. Concrete has been poured for the foundations.
  • Draugu iela 17: paving works are complete, and polished concrete (Ultratop) has been poured.
  • Draugu iela 21 - installation works of the heat recovery ventilation system, as well as the ceiling vapour barrier, have been completed.
  • Guest House - construction of the first floor load-bearing frame has been completed.

  • 178,4 tons of crushed stone were delivered on site
  • 3,5 cubic meters of semi-dry concrete were for building foundations

If you have any questions, please don't hesitate to contact us at info@asterra.estate .

You may like these articles:

article
March 6, 2026
5 min

Asterra Estate February performance overview

February may have been short, but it was a highly productive month for Asterra Estate. Infrastructure works for Phase 2, including utility installation and road construction, are underway and expected to continue for approximately four more months.

article
March 2, 2026
5 min

Build & benefit bonus campaign

The Asterra Estate team likes to set big goals and challenge ourselves. Our main goal for 2026 is to build 31 new residential houses (in addition to the houses already under construction) and to complete the landscaping and surrounding infrastructure for these properties.

article
February 18, 2026
4 min

We are launching the Asterra Estate Loyalty program

We’re incredibly proud of what we’ve accomplished at Asterra Estate in such a short time, together with our lenders. What we’re building goes beyond real estate - it’s a long-term partnership and steady growth, especially with the continued development of Asteres Village.