Blog

January 7, 2026
4 min

Asterra December performance overview

article

December was a productive month for Asterra Estate. Alongside consistent platform activity, the community continued to grow— over the past seven months, Asterra Estate has reached more than 700 loyal lenders, with more than €5 million committed to the project. During the month, we also activated the Early Exit option for the first projects, giving investors greater flexibility, and shared plans to expand beyond residential development with a CLT & GLT production factory to support more efficient construction and long-term growth.

At the same time, progress across the village remained steady, with multiple houses advancing through interior, exterior, and infrastructure works. Below you’ll find a detailed overview of the platform’s key indicators and the latest project statuses from the village.

Platform key indicators

  • €626,708 mezzanine loans attracted
  • €87,770 interest earned
  • 16.03% average interest rate
  • €6,679 average funding amount
  • 87 new active lenders joined Asterra

Village project statuses

  • Draugu iela 6 - interior works (wall painting, plastering and tiling, also installation of parquet and interior doors) and furniture placement and assembly
  • Draugu iela 8 - completed work on the terrace construction. Installed polished concrete (Ultratop) floors. Started construction of an outdoor utility room and front deck, and also began interior works (tiling and plastering).
  • Draugu iela 11 - wall and ceiling painting, plastering and tiling works have been completed. Started construction of an outdoor utility room. Completed installation of exterior doors
  • Draugu iela 13 - completed installation of drywall installation on the ceilings. Installation of the facade board and CLT sanding has started
  • Draugu iela 14: construction of the sewage network and assembly of the foundation formwork have been completed. Concrete has been poured for the foundations.
  • Draugu iela 17: paving works are complete, and polished concrete (Ultratop) has been poured.
  • Draugu iela 21 - installation works of the heat recovery ventilation system, as well as the ceiling vapour barrier, have been completed.
  • Guest House - construction of the first floor load-bearing frame has been completed.

  • 178,4 tons of crushed stone were delivered on site
  • 3,5 cubic meters of semi-dry concrete were for building foundations

If you have any questions, please don't hesitate to contact us at info@asterra.estate .

You may like these articles:

article
December 23, 2025
2 min

Asterra Estate Holiday Schedule

As the holiday season approaches, the Asterra Estate team will be working on a holiday schedule from December 24–29 and December 31–January 5.

article
December 16, 2025
5 min

CLT & GLT Factory: A New Step in Asterra Estate’s Growth

Asterra Estate has an exciting year ahead, as the team is expanding its activities beyond residential development with the establishment of a CLT & GLT production factory. The facility will support existing developments while also operating as an independent business line for the group. This step reflects Asterra Estate’s continued focus on vertical integration, operational efficiency, and long-term value creation.

article
December 11, 2025
8 min

Early Exit is active for some projects

In just seven months, Asterra Estate has grown into a strong community of over 700 active lenders, with nearly €5 million already committed to the project's development. To make the investment process more flexible and comfortable, the Early Exit option has become one of the key elements of the Asterra Estate platform. This feature is designed to provide investors with additional liquidity and greater control over their capital.