Blog

December 4, 2025
4 min

Asterra November performance overview

article

November has been another busy month at Asteres Village. Construction kept going strong - we kicked off work on eight homes in total - seven residential homes and one guest house. Some houses are already getting their windows and facades done, others have foundations and roofs in place, and inside these homes, the team is busy with sanding, painting, and installing underfloor heating. All in all, things are really starting to take shape!

On the platform side, activity remained aligned with the company’s needs. We welcomed 30 new lenders, bringing the total to 710, and raised €316,968 in new funding. The total funding available is now €795,000, and our lenders earned €62,324 in interest at an average rate of 16.11%.

Sales are moving too, with plenty of visitors stopping by the village to see the progress firsthand. The village is starting to feel like a real community!

Platform key indicators

  • Total funding available on the platform - 795,000
  • Lenders joined - 30 (total active lenders - 710)
  • New funding attracted - 316,968 (total funding - €4,617,918)
  • Lenders' interest earned in the given month - 62,324 (total - 435,481)
  • Average interest rate - 16.11%

Village project statuses

Brief status report on construction works in Asteres Village during November.

  • Construction work has commenced on seven houses and one guest house.
    • Draugu 6 - various indoor and finishing works - sanding and painting of CLT panels, plastering works. A heat pump has been installed.
    • Draugu 8 - completed paving and facade works. Work on drywall installation on the ceiling has begun.
    • Draugu 11 - facade works have been done. CLT panel sanding work has started.
    • Draugu 13 - window installation has completed. Paving works have been started
    • Draugu 14 - foundation has been excavated.
    • Draugu 17 - completed installation of windows and underfloor heating system. Electrical installation has begun.
    • Draugu 21 - completed installation of CLT and roof assembly.
    • Asteru 2 - the building permit is still in the approval process. Construction works have not yet started.
    • Guest house - foundation works have been completed.

  • Active sales operations continue, resulting in potential buyers visiting the Village.
  • Construction Materials Used:
    • 78,4 tons of crushed stone delivered.
    • 32 cubic meters of ready-mix concrete were used for building foundations.
    • 15 cubic meters of dry-mix concrete were delivered.

P.S. Plus, the Christmas campaign is still open, giving you instant cashback — and a chance to win a weekend trip to Asterra Estate and see the project for yourself.


You may like these articles:

article
March 6, 2026
5 min

Asterra Estate February performance overview

February may have been short, but it was a highly productive month for Asterra Estate. Infrastructure works for Phase 2, including utility installation and road construction, are underway and expected to continue for approximately four more months.

article
March 2, 2026
5 min

Build & benefit bonus campaign

The Asterra Estate team likes to set big goals and challenge ourselves. Our main goal for 2026 is to build 31 new residential houses (in addition to the houses already under construction) and to complete the landscaping and surrounding infrastructure for these properties.

article
February 18, 2026
4 min

We are launching the Asterra Estate Loyalty program

We’re incredibly proud of what we’ve accomplished at Asterra Estate in such a short time, together with our lenders. What we’re building goes beyond real estate - it’s a long-term partnership and steady growth, especially with the continued development of Asteres Village.