Blog

November 5, 2025
5 min

Asterra October performance overview

article

In October, we continued steady development activity at Asteres Village, with construction progressing on multiple residential buildings and supporting infrastructure. Work progressed on six houses and a guest house, and preparation work continued in the Phase Two territory. In addition, production of one CLT building was completed at the factory.

The month also saw ongoing interest from potential buyers through on-site visits. Looking ahead, the demo house will be opened in mid-November, marking an important step in the sales process and offering potential buyers the opportunity to explore the village concept and building quality firsthand.

On the Asterra platform, funding activity remained stable and aligned with village development needs, supporting the project's long-term progress.

Platform key indicators

  • Total funding available on the platform - 500,000
  • Lenders joined - 88 (total active lenders - 680)
  • New funding attracted - 702,141 (total funding - €4,300,950)
  • Lenders' interest earned in the given month - 79,904 (total - 373,157)
  • Average interest rate - 16.12%

Village project statuses

Brief status report on construction works in Asteres Village during October.

  • Construction work has commenced on six houses, one guest house, and on phase two territory.
    • Draugu 6 - various indoor works - sanding and painting of CLT panels, tiling and waterproofing works, completed designer floor installation. Fence construction is still in progress.
    • Draugu 8 - underfloor heating was installed, dry concrete (Estrich) was laid, and house insulation works were done. Installation of vertical and horizontal battens was completed.
    • Draugu 11 - completed electrical installation and facade installation; also completed building drywall partitions. Landscaping and gardening works were done.
    • Draugu 13 - CLT assembly work is complete, and roof trusses have been installed, along with vapour barrier insulation.
    • Draugu 17 - completed installation of CLT and roof frame assembly
    • Draugu 21 - foundation works completed. Built a driveway.
    • Asteru 2 - The building permit is in the approval process. Construction works have not yet started.
    • Guest house - the old building has been demolished, and foundation work of the new building has started.
    • Phase 2 - approximately 20,000 m³ of sand have been excavated from the small lake/quarry within the village

  • Manufacturing of one CLT building (Draugu 21) has been completed in the factory.
  • Active sales operations continue, resulting in potential buyers visiting the Village.

  • Construction Materials Used:
    • 52,9 tons of crushed stone delivered.
    • 9 cubic meters of ready-mix concrete were used for building foundations.
    • 18 cubic meters of sand were delivered.

You may like these articles:

article
December 4, 2025
4 min

Asterra November performance overview

November has been another busy month at Asteres Village. Construction kept going strong - we kicked off work on eight homes in total - seven residential homes and one guest house. Some houses are already getting their windows and facades done, others have foundations and roofs in place, and inside these homes, the team is busy with sanding, painting, and installing underfloor heating. All in all, things are really starting to take shape!

article
November 24, 2025
3 min

This holiday, your bonus might come with a boarding pass to Asterra Estate.

The holiday season is almost here, and at Asterra Estate, we’re celebrating with something special. This year, your investments might send you on a weekend getaway to one of Latvia’s most charming new real estate developments.

article
November 14, 2025
1 min

Support availability during National Holidays

🇱🇻 Latvia’s Independence Day is almost here, and our Asterra Estate team will be off celebrating from November 15th to 18th.