Blog

November 5, 2025
5 min

Asterra October performance overview

article

In October, we continued steady development activity at Asteres Village, with construction progressing on multiple residential buildings and supporting infrastructure. Work progressed on six houses and a guest house, and preparation work continued in the Phase Two territory. In addition, production of one CLT building was completed at the factory.

The month also saw ongoing interest from potential buyers through on-site visits. Looking ahead, the demo house will be opened in mid-November, marking an important step in the sales process and offering potential buyers the opportunity to explore the village concept and building quality firsthand.

On the Asterra platform, funding activity remained stable and aligned with village development needs, supporting the project's long-term progress.

Platform key indicators

  • Total funding available on the platform - 500,000
  • Lenders joined - 88 (total active lenders - 680)
  • New funding attracted - 702,141 (total funding - €4,300,950)
  • Lenders' interest earned in the given month - 79,904 (total - 373,157)
  • Average interest rate - 16.12%

Village project statuses

Brief status report on construction works in Asteres Village during October.

  • Construction work has commenced on six houses, one guest house, and on phase two territory.
    • Draugu 6 - various indoor works - sanding and painting of CLT panels, tiling and waterproofing works, completed designer floor installation. Fence construction is still in progress.
    • Draugu 8 - underfloor heating was installed, dry concrete (Estrich) was laid, and house insulation works were done. Installation of vertical and horizontal battens was completed.
    • Draugu 11 - completed electrical installation and facade installation; also completed building drywall partitions. Landscaping and gardening works were done.
    • Draugu 13 - CLT assembly work is complete, and roof trusses have been installed, along with vapour barrier insulation.
    • Draugu 17 - completed installation of CLT and roof frame assembly
    • Draugu 21 - foundation works completed. Built a driveway.
    • Asteru 2 - The building permit is in the approval process. Construction works have not yet started.
    • Guest house - the old building has been demolished, and foundation work of the new building has started.
    • Phase 2 - approximately 20,000 m³ of sand have been excavated from the small lake/quarry within the village

  • Manufacturing of one CLT building (Draugu 21) has been completed in the factory.
  • Active sales operations continue, resulting in potential buyers visiting the Village.

  • Construction Materials Used:
    • 52,9 tons of crushed stone delivered.
    • 9 cubic meters of ready-mix concrete were used for building foundations.
    • 18 cubic meters of sand were delivered.

You may like these articles:

article
December 23, 2025
2 min

Asterra Estate Holiday Schedule

As the holiday season approaches, the Asterra Estate team will be working on a holiday schedule from December 24–29 and December 31–January 5.

article
December 16, 2025
5 min

CLT & GLT Factory: A New Step in Asterra Estate’s Growth

Asterra Estate has an exciting year ahead, as the team is expanding its activities beyond residential development with the establishment of a CLT & GLT production factory. The facility will support existing developments while also operating as an independent business line for the group. This step reflects Asterra Estate’s continued focus on vertical integration, operational efficiency, and long-term value creation.

article
December 11, 2025
8 min

Early Exit is active for some projects

In just seven months, Asterra Estate has grown into a strong community of over 700 active lenders, with nearly €5 million already committed to the project's development. To make the investment process more flexible and comfortable, the Early Exit option has become one of the key elements of the Asterra Estate platform. This feature is designed to provide investors with additional liquidity and greater control over their capital.