Blog

November 5, 2025
5 min

Asterra October performance overview

article

In October, we continued steady development activity at Asteres Village, with construction progressing on multiple residential buildings and supporting infrastructure. Work progressed on six houses and a guest house, and preparation work continued in the Phase Two territory. In addition, production of one CLT building was completed at the factory.

The month also saw ongoing interest from potential buyers through on-site visits. Looking ahead, the demo house will be opened in mid-November, marking an important step in the sales process and offering potential buyers the opportunity to explore the village concept and building quality firsthand.

On the Asterra platform, funding activity remained stable and aligned with village development needs, supporting the project's long-term progress.

Platform key indicators

  • Total funding available on the platform - 500,000
  • Lenders joined - 88 (total active lenders - 680)
  • New funding attracted - 702,141 (total funding - €4,300,950)
  • Lenders' interest earned in the given month - 79,904 (total - 373,157)
  • Average interest rate - 16.12%

Village project statuses

Brief status report on construction works in Asteres Village during October.

  • Construction work has commenced on six houses, one guest house, and on phase two territory.
    • Draugu 6 - various indoor works - sanding and painting of CLT panels, tiling and waterproofing works, completed designer floor installation. Fence construction is still in progress.
    • Draugu 8 - underfloor heating was installed, dry concrete (Estrich) was laid, and house insulation works were done. Installation of vertical and horizontal battens was completed.
    • Draugu 11 - completed electrical installation and facade installation; also completed building drywall partitions. Landscaping and gardening works were done.
    • Draugu 13 - CLT assembly work is complete, and roof trusses have been installed, along with vapour barrier insulation.
    • Draugu 17 - completed installation of CLT and roof frame assembly
    • Draugu 21 - foundation works completed. Built a driveway.
    • Asteru 2 - The building permit is in the approval process. Construction works have not yet started.
    • Guest house - the old building has been demolished, and foundation work of the new building has started.
    • Phase 2 - approximately 20,000 m³ of sand have been excavated from the small lake/quarry within the village

  • Manufacturing of one CLT building (Draugu 21) has been completed in the factory.
  • Active sales operations continue, resulting in potential buyers visiting the Village.

  • Construction Materials Used:
    • 52,9 tons of crushed stone delivered.
    • 9 cubic meters of ready-mix concrete were used for building foundations.
    • 18 cubic meters of sand were delivered.

You may like these articles:

article
October 9, 2025
5 min

Asterra September performance overview

In September, Asterra Estate continued active construction work at Asteres Village. Progress on the ground remained strong, with six buildings currently under construction and individual houses moving through different stages of development. In addition, work has also begun on a new luxury villa project within the Asteres Village area.

article
August 29, 2025
3 min

Big autumn plans. Perfectly matched cashback

At Asterra Estate, every investment creates value - both for our investors and for the communities we are building. This autumn, we are pleased to introduce our new campaign - “Big autumn plans. Perfectly matched cashback.” From August 29 to October 31, 2025, all investments made in Asterra Estate projects will receive a 4% cashback bonus. The offer applies to every project on the platform, providing investors with the opportunity to enhance their returns while supporting the steady progress of Asterra Village.

article
August 8, 2025
4 min

Performance report. July

July marked the second month of Asterra Estate’s active operations, and the project continued to gain impressive traction in both investor engagement and construction progress. Lenders remained highly involved, contributing a total of €1.388 million in funding for Asterra Village projects during the month alone — a strong indicator of growing confidence in the development’s vision and potential.