Asterra September performance overview

article

In September, Asterra Estate continued active construction work at Asteres Village. Progress on the ground remained strong, with six buildings currently under construction and individual houses moving through different stages of development. In addition, work has also begun on a new luxury villa project within the Asteres Village area.

Site preparation also advanced in the Asteres Village Stage 2 area. During this period, work permits were requested from Sadales tīkls (ST), GASO, and the Real Estate Department of the Ministry of Agriculture. In addition, surveying work was carried out, including the marking of red lines and pond points, as well as staking out protective zones and other preparatory activities.

This month, we also welcomed a new team member — Madara Balode, a sales expert with extensive experience in the Ādaži real estate market. Madara is a proven top performer in the region, and we are excited to have her strengthen our sales team.

Platform key indicators

  • Total funding available on the platform - 500,000
  • Lenders joined - 119 (total active lenders - 592)
  • New funding attracted - 720,686 (total funding - €3,598,808)
  • Lenders' interest earned in the given month - 72,354 (total - 293,252)
  • Average interest rate - 16.24%

Village project statuses

Brief status report on construction works in Asteres Village during September.

  • Construction work has commenced on six houses.
    • Draugu 8 - installation of the roof and heat recovery system has been completed.
    • Draugu 13 - CLT assembly work is complete, and roof trusses have been installed.
    • Draugu 17 - foundation constructions are completed, external utilities have been installed
    • Draugu 21 - foundation works - crushed stones were laid, and foam insulation has been installed.
    • Draugu 11 - facade insulation works, window installation, and partition wall construction have been completed. Underfloor heating installations and facade battening works were completed. Estrich dry concrete has been installed.
    • Draugu 6 - completed landscaping and land grading works. Interior works - spackling and tiling have been completed, as well as the installation of mirror film on the windows.
    • Asteru2

In September, work began on a new, exclusive development project in the Asterra Estate area.

A purchase agreement has been signed with the buyer for the construction of a luxury villa, and the first payment has already been received. Currently, building design and planning are underway, along with land and site preparation for construction.

The project will occupy an 8,510 m² land plot and feature a 1,095 m² luxury villa at Asteru Street 2.

  • Manufacturing of two CLT buildings (Draugu 13 and 17) has been completed in the factory.
  • Active sales operations continue, resulting in potential buyers visiting the Village.
  • Construction Materials Used:
    • 185 tons of crushed stone delivered.
    • 29,5 cubic meters of ready-mix concrete were used for building foundations.
    • 90 cubic meters of sand were delivered.

You may like these articles:

article
November 24, 2025
3 min

This holiday, your bonus might come with a boarding pass to Asterra Estate.

The holiday season is almost here, and at Asterra Estate, we’re celebrating with something special. This year, your investments might send you on a weekend getaway to one of Latvia’s most charming new real estate developments.

article
November 14, 2025
1 min

Support availability during National Holidays

🇱🇻 Latvia’s Independence Day is almost here, and our Asterra Estate team will be off celebrating from November 15th to 18th.

article
November 5, 2025
5 min

Asterra October performance overview

In October, we continued steady development activity at Asteres Village, with construction progressing on multiple residential buildings and supporting infrastructure. Work progressed on six houses and a guest house, and preparation work continued in the Phase Two territory. In addition, production of one CLT building was completed at the factory.