Asterra September performance overview

article

In September, Asterra Estate continued active construction work at Asteres Village. Progress on the ground remained strong, with six buildings currently under construction and individual houses moving through different stages of development. In addition, work has also begun on a new luxury villa project within the Asteres Village area.

Site preparation also advanced in the Asteres Village Stage 2 area. During this period, work permits were requested from Sadales tīkls (ST), GASO, and the Real Estate Department of the Ministry of Agriculture. In addition, surveying work was carried out, including the marking of red lines and pond points, as well as staking out protective zones and other preparatory activities.

This month, we also welcomed a new team member — Madara Balode, a sales expert with extensive experience in the Ādaži real estate market. Madara is a proven top performer in the region, and we are excited to have her strengthen our sales team.

Platform key indicators

  • Total funding available on the platform - 500,000
  • Lenders joined - 119 (total active lenders - 592)
  • New funding attracted - 720,686 (total funding - €3,598,808)
  • Lenders' interest earned in the given month - 72,354 (total - 293,252)
  • Average interest rate - 16.24%

Village project statuses

Brief status report on construction works in Asteres Village during September.

  • Construction work has commenced on six houses.
    • Draugu 8 - installation of the roof and heat recovery system has been completed.
    • Draugu 13 - CLT assembly work is complete, and roof trusses have been installed.
    • Draugu 17 - foundation constructions are completed, external utilities have been installed
    • Draugu 21 - foundation works - crushed stones were laid, and foam insulation has been installed.
    • Draugu 11 - facade insulation works, window installation, and partition wall construction have been completed. Underfloor heating installations and facade battening works were completed. Estrich dry concrete has been installed.
    • Draugu 6 - completed landscaping and land grading works. Interior works - spackling and tiling have been completed, as well as the installation of mirror film on the windows.
    • Asteru2

In September, work began on a new, exclusive development project in the Asterra Estate area.

A purchase agreement has been signed with the buyer for the construction of a luxury villa, and the first payment has already been received. Currently, building design and planning are underway, along with land and site preparation for construction.

The project will occupy an 8,510 m² land plot and feature a 1,095 m² luxury villa at Asteru Street 2.

  • Manufacturing of two CLT buildings (Draugu 13 and 17) has been completed in the factory.
  • Active sales operations continue, resulting in potential buyers visiting the Village.
  • Construction Materials Used:
    • 185 tons of crushed stone delivered.
    • 29,5 cubic meters of ready-mix concrete were used for building foundations.
    • 90 cubic meters of sand were delivered.

You may like these articles:

article
August 29, 2025
3 min

Big autumn plans. Perfectly matched cashback

At Asterra Estate, every investment creates value - both for our investors and for the communities we are building. This autumn, we are pleased to introduce our new campaign - “Big autumn plans. Perfectly matched cashback.” From August 29 to October 31, 2025, all investments made in Asterra Estate projects will receive a 4% cashback bonus. The offer applies to every project on the platform, providing investors with the opportunity to enhance their returns while supporting the steady progress of Asterra Village.

article
August 8, 2025
4 min

Performance report. July

July marked the second month of Asterra Estate’s active operations, and the project continued to gain impressive traction in both investor engagement and construction progress. Lenders remained highly involved, contributing a total of €1.388 million in funding for Asterra Village projects during the month alone — a strong indicator of growing confidence in the development’s vision and potential.

article
July 10, 2025
2 min

Performance report. June

The first month of Asterra Estate has been marked by very high activity, particularly on the 36-hectare land plot in Asteres Village. Infrastructure development works have continued steadily, and construction of the first five houses has begun. We are also pleased to report a remarkable level of interest from P2P industry lenders. Within just 15 days in June, a total of €1,330,782 was successfully funded.