Blog

July 10, 2025
2 min

Performance report. June

article

The first month of Asterra Estate has been marked by very high activity, particularly on the 36-hectare land plot in Asteres Village. Infrastructure development works have continued steadily, and construction of the first five houses has begun.

We are also pleased to report a remarkable level of interest from P2P industry lenders. Within just 15 days in June, a total of €1,330,782 was successfully funded.

Platform key indicators
  • Projects available on the platform - 6
  • Total funding available on the platform - 1,685,000
  • Lenders joined - 262
  • Funding attracted - 1,330,782
  • Interest earned - 84,970
  • Average interest rate - 16.12%

Village project statuses

Brief status report on construction works in Asteres Village during June.

  • 5 additional building permits have been received
  • Construction work has commenced on five houses
    • Draugu 11 – foundation construction completed
    • Draugu 8, 13, 17, 21 – land preparation and foundation construction are underway
  • Manufacturing of two CLT buildings (Draugu 8 and 11) has started in the factory
  • Active sales operations began in June, resulting in the first potential buyer visits to the Asteres village
  • Construction Materials Used:
    • 160 tons of crushed stone delivered
    • 150 tons of sand delivered
    • 30 cubic meters of concrete used for building foundations
    • 3 tons of reinforcement steel used

You may like these articles:

article
December 23, 2025
2 min

Asterra Estate Holiday Schedule

As the holiday season approaches, the Asterra Estate team will be working on a holiday schedule from December 24–29 and December 31–January 5.

article
December 16, 2025
5 min

CLT & GLT Factory: A New Step in Asterra Estate’s Growth

Asterra Estate has an exciting year ahead, as the team is expanding its activities beyond residential development with the establishment of a CLT & GLT production factory. The facility will support existing developments while also operating as an independent business line for the group. This step reflects Asterra Estate’s continued focus on vertical integration, operational efficiency, and long-term value creation.

article
December 11, 2025
8 min

Early Exit is active for some projects

In just seven months, Asterra Estate has grown into a strong community of over 700 active lenders, with nearly €5 million already committed to the project's development. To make the investment process more flexible and comfortable, the Early Exit option has become one of the key elements of the Asterra Estate platform. This feature is designed to provide investors with additional liquidity and greater control over their capital.